A construction boom at Coega Industrial Development Zone | Infrastructure news

Building projects in the Coega Industrial Development Zone (IDZ) have injected over R1.2 billion into the Nelson Mandela Bay construction industry over the past two quarters.

Six major construction projects are currently underway in the Coega IDZ including erection of:

  • Chinese car and truck manufacturer First Automobile Works’ (FAW) plant;
  • Famous Brands’ cold storage plant;
  • DCD Group’s wind tower manufacturing plant;
  • the addition of Coega Cheese onto the Coega Dairy outfit;
  • Agni Steels’ R400-million smelter facility; and
  • Rehau’s extension in the Nelson Mandela Bay Logistics Park (NMBLP).
Industrial gas company,Air Products South Africa, isalso about to begin construction of its R300 million state-of-the-art air separation unit in Zone 3 inJuly, bringing the total number of projects being built to seven.

“The global economic climate is still not stable, yet investment continues to flow into the Coega IDZ and is literally taking root in the construction projects underway,” says Ayanda Vilakazi, Coega Development Corporation (CDC) head of marketing and communications.

“We currently have 20 operational investors, and once these seven construction projects are complete, we will be up to 27 operational investors by mid-2014.”

Vilakazi says the activity meant major spinoffs not only for lead contractors, but also sub-contractors, suppliers and the whole built environment supply chain:

“At a time when there is industry malaise at a national level, the Coega IDZ is experiencing a construction boom to the value of R1.2-billion.

“The unaudited results 2012/13 financial year also show that construction jobsin the Coega, IDZ and the NMBLP for April 2012 to March 2013 amount to 1722 and investor jobs created are at about 856 – so just over 2500 jobs created directly through activity in the Coega IDZ,” says Vilakazi, adding that it was through these major investments that the CDC was delivering on its mandate to create jobs.

Famous Brands

The Famous Brands project is nearest completion and the company wasgiven access to the warehouse portion in the first week of Mayallowingits service provider to start with racking on the warehouse floor. The warehouse is operational and Famous Brands will move its stock into the cold storage unit on June 10.

“Everything is on track, with timeframes tight but on target to be met. The project is still well within original time, cost and quality parameters set – despite loss of a number of days due to inclement weather, mainly wind and rain,” saysBruno Ponzi, CDC senior project manager for infrastructure development.

The company – which owns the likes of Steers and Debonairs –was also given access to the ground floor of the office block portion this week,with the balance of the building due for hand over on June 21. Once delivered Famous Brands would become the newest operational tenant in the Coega IDZ.

Vilakazi says Famous Brands was a prime example of the short conversion times investors experience from the point of signing a lease with the CDC tofull operation.

“The turnaround times are much quicker now than they were a couple of years ago and we are able to construct buildings for investors relatively quickly, meaning that they move to operational phase within about a year of signing, depending on this size of the project,” said Vilakazi. “This has implications for investors’ bottom dollar as they are able to start productionrelatively quickly.”

A partnership between Famous Brands and Coega Dairy has also seen the dairy expanding its operations to supply cheese products to the group in a project dubbed ‘Coega Cheese’ with a joint valued investment of R45 million pouring into the Coega IDZ as a result.

FAW

In addition, says Vilakazi, the construction activity is creating needed jobs on the city, particularly on the FAW site, with the R200 million FAWconstruction project well underway. To date about 304 construction jobs have been created on its site, a number that grows week to week. In total the construction phase will see about 2000 jobs generated over the year-long duration. In the operation phase of the truck assembling plant a further 280 jobs will also be created.

According to Arnie van Jaarsveldt, WBHO Construction Eastern Cape managing director and lead contractor on the FAW project, the highlight of the construction will be its architectural finesse.

Van Jaarsveldt saysEastern Cape Architects Studio d’Arc wanted to make a statement with the Chinese automotive giants’ building in Zone 2 of the IDZ.

“Its prime position on the N2 means it will get heightened attention. FAW management loved Studio d’Arc’s unique design on the office and reception area – particularly the exceptional use of concrete, so that’s set to be the highlight of the building,” says van Jaarsveldt.

“Otherwise, we are working hard to keep to a strict timetable, and you will see the columns almost completed and some initial top structures going up over the factory portion. With a long way to go, the skeleton is definitely taking shape.”

Van Jaarsveldt said construction is on-track for completion end December 2013, adding that there was significant collaboration between the Chinese engineers and their South African counterparts – a coup for skills development and mentorship.

AGNI STEELS

AgniSteels is also wrapping construction of its R400 million steel plant in Zone 6 of the 11500Ha IDZ. Agni Steels will operate in a high-tech smelting facility to produce mild steel billets from scrap metal. The plant at Coega will use 10 000 tons of scrap metal in phase 1 and 20 000 tons in phase 2.

DCD GROUP

DCD Group is also in the early phases of its R300 million wind tower manufacture factory which when completed, is expected to employ 168 workers, and produce between 110 and 120 wind towers annually.

“Coega is boldly delivering on our jobs promise through the attraction of investments,” says Vilakazi.

Additional Reading?

Request Free Copy