Unit 4 at Eskom’s Medupi Power Station Project in Lephalale, Limpopo, has attained commercial operation status. In a statement release on Tuesday the power utility said the unit reached its full power on 19 June 2017 just 20 days after its successful synchronisation on 31 May 2017. Five months later, after further tests were conducted, Unit 4 has now been declared in full commercial operation ahead of the scheduled timeline of July 2018. With an output of 794 megawatts going to the national grid, Unit 4 joins its sister units, Unit 6 and 5, which have been contributing to the balancing of electricity supply and demand since 23 August 2015 and 3 April 2017 respectively. “We are proud of this achievement. This accomplishment is a reflection of hard work and team effort. Eskom applauds the Medupi team, under the leadership of Phillip Dukashe. This is indeed an embodiment of delivery and excellence. Well done to the Medupi team!” said Peter Sebola, Acting Group Executive, Group Capital Division.
What else to read
Additional Reading?
Request Free CopyRelated Articles
Jul 1, 2024
Tackling Africa’s water crisis: ‘Too little, Too much, Too dirty’
Generally speaking, water management disaster scenarios in water-challenged countries such as South Africa present one of three problems: too little, too much or too dirty. SRK Consulting senior technologist and disaster management consultant...
Feb 7, 2025
Infrastructure to Guide South Africa’s Growth
The 2025 state of the nation address was a call for collaboration across the sectors, both public and private, to pull together in order to grow South Africa’s economy. President Cyril Ramaphosa highlighted the backdrop that South Africa finds...
Nov 20, 2024
Lepelle Northern Water Contractor And Engineers Complete Work Ahead Of Schedule
Lepelle Northern Water (LNW) team of engineers and contractor has completed the replacement of the old sections and commissioning of the new pipelines that were at risk in the Mankweng area. As of 6:00 am this morning, 20 November 2024, the LNW...