The Tongaat Water Treatment Works (TWTW) was one of the hardest hit pieces of water and sanitation infrastructure in last year’s April floods in KwaZulu-Natal. It resulted in water supply issues for nearly 90 000 people.
By Kirsten Kelly
“During the floods, the Tongaat Dam overtopped, causing substantial damage to the TWTW downstream,” says Bhavna Soni, deputy head: eThekwini Water and Sanitation (EWS), eThekwini Metropolitan Municipality. Before: The TWTW was one of the hardest hit pieces of water and sanitation infrastructure in last year’s April floods The access road to the TWTW (on land owned by Tongaat Hulett) was washed away and no repairs or even a comprehensive assessment of the damage to the treatment works could be done until a new road was built. Other damage included:
The motor control centre (MCC) was located underground within the pump house, and both were submerged in nearly 4 m of water – destroying all electrical equipment and damaging mechanical systems like the pumps, motors, instrumentation and control systems.
A lot of silt and rocks were found in the clarifiers and some of them were severely damaged.
The head of works channel was significantly damaged and founding material washed away. This channel settled and required significant repairs, including being jacked back into position.
The floods also caused substantial erosion, resulting in the undermining of the chemical and chlorine building foundations.
Most interconnecting pipework, cabling and ducting on-site was damaged.
Tongaat Hulett assisted with rebuilding the road and repairing the raw water steel pipeline – which was completed in just over a month. The pipeline reinstatement followed the road repair. Finding alternative water sources for the area was EWS’s first priority. Three projects were expedited to bring relief:
Fast-track the tie-in of the Mamba Ridge pipeline from the Hazelmere Waterworks to the Mamba Ridge Reservoir. Once completed, this resulted in directing 2 Mℓ of water a day from the Hazelmere Water Treatment Plant to some parts of oThongathi.
Supplying water from the Belvedere Reservoir (cross connection to Hazelmere System).
Laying a water main to the Tongaat South Reservoir from the Nyaninga Reservoir, using eThekwini Municipality’s in-house construction team as far as possible in order to bypass the lengthy procurement process.
After: The repair of the TWTW was completed within the agreed upon 15 weeks or 105 days (13 July to 27 October 2022)
Professional team
Section 36 of the Municipal Supply Chain Management Regulations was invoked to speed up the procurement process and acquire funding. Section 36 falls within the Municipal Finance Management Act (No. 56 of 2003), to select who will carry out a particular contract. eThekwini used a quotation process and a Naidu Consulting/MSW Consulting joint venture appointed as the consultant, Icon Construction was appointed as the contractor, with PCI Africa as a subcontractor for the mechanical, electrical, instrumentation, automation and control work. The Naidu Consulting/MSW JV did the initial damage assessments and produced multiple options to ensure the restoration of the water supply to the Tongaat area. “We also did a full assessment to determine a baseline for the work that needed to be undertaken to restore the plant to operation, including assessing various approaches to the remediation woks and produced the applicable emergency tender documentation for this contract,” states Devesh Ramghulam, technologist, Naidu Consulting. After: 15 km of cabling was installed
An extensive amount of support was received from the Tongaat community, which played a significant role in avoiding project delays The plant was originally constructed by Tongaat Hulett before it was taken over (operationally) by eThekwini Municipality in 2001. In 2014, eThekwini had complete ownership of the TWTW.
“While Tongaat Hulett no longer owns the TWTW, a substantial amount of damage was caused to its own water infrastructure and it has been a huge support in the restoration of the TWTW. In addition to repairing the access road and raw water pipeline, the company allowed a part of the new MCC to be built on its land,” explains Soni.
Designs on foundations of the chemical and chlorine building, as well as the inlet pipe and underpinning, were completed on-site to ensure structures were safe, accessible and suitable for future use. This was done in short timeframes to enable access to other areas of the site. “Due to the nature of the ground conditions and surrounding buildings, heavy vibratory equipment could not be used beneath structures, and therefore applicable concrete underpinning was implemented,” explains Ramghulam. The clarifiers had to be drained, cleared of rocks and have mud pumped from them All six clarifiers were filled with 2-3 m of debris. They had to be drained, cleared of stones and sand, and have mud pumped out of them. “This was a complicated process because the clarifiers are over 9 m deep, the sides are sloped at 60-degree angles, and people had to work inside the clarifiers. The sand filters had to be cleaned and backwashed, and channels had to be cleaned. Most of the digging could not be done by machine because the site was small, so most of the work required a lot of manual labour,” states Hope. As the TWTW is a few decades old, there was no detailed, updated plan of the layout, which made it difficult to reinstate all of the pipelines. “We were unsure as to what was underneath the pump station and had to figure out what pump went where. PCI Africa therefore had to make changes to some of the pipework,” says Hope. PCI Africa took charge of reinstating or replacing the pumps.“The existing MCC housing the old electrical and control systems, comprising 20 starters, was completely destroyed, and was therefore discarded. All the mechanical equipment had to be removed for inspection. Most of the bigger pumps were repaired while the smaller units were replaced,” adds Rathebe.
Building back better
After: Gabion baskets were installed around the TWTW to protect it from future erosion. The new MCC building is in the background To avoid damage caused by future floods, a decision was made prior to the commencement of the Contract by EWS and the Naidu Consulting/MSW JV to move the MCC from the pump room to a higher elevation in a separate building, between 55 m and 75 m away. The newly designed and built MCC was installed (as the support work was being removed from the new structure) with the associated electrical and control cabling and racking. The eleven rising main pump sets, backwash pumps, blowers, as well as fans in the pump room are managed from the MCC room – resulting in 15 km of cable being installed. A concrete culvert was constructed to protect the cables that run from the pump room to the MCC, which also expedited the cable-laying activities. Other protection works included gabion baskets around the TWTW to protect it from future erosion, while a separate stormwater channel was constructed to direct water away from the building. For additional security, a new fence was constructed around the TWTW and existing roads were rehabilitated.
Commissioning
Before commissioning the TWTW, all five reservoirs were inspected, cleaned, disinfected and the water quality was tested. Since the entire system had not been in operation for months, it was therefore expected that there would be multiple pipe bursts once the TWTW was commissioned. However, this did impede efforts to build capacity in the reservoirs. One trunk main and reservoir was commissioned at a time so that the EWS team could focus on a particular zone and immediately resolve any issues that may arise. Naidu Consulting was actively involved in the commissioning activities and its project team also assisted EWS with assessing the situation, identifying the bursts and fast-tracking the pipeline reinstatement. “The Hambanathi area had no alternative water supply (other than water tankers) and was therefore the first community to receive water from the newly repaired TWTW. In addition to burst pipes, another challenge was that water demand in the area was high, as community members were storing water. We therefore made the decision to run two pumps in parallel, with a third pump as a backup,” adds Soni. Another challenge was that the Emona pipeline was old and required extensive repairs. Fortunately, this was resolved because a trunk main at the newly built Emona Reservoir was being built and fast-tracked to replace that old pipeline. The Mamba Ridge area has also experienced some difficulties, with a suspected burst trunk; however, there is an alternative supply from Hazelmere.
Phase 2
Originally designed for 21 Mℓ/day, the TWTW is currently operating at 14 Mℓ/day. The Naidu Consulting/MSW JV has been appointed to design the TWTW’s functional upgrade. Currently, EWS has limited abstraction rights from the Tongaat Dam, which restricts the plant’s capacity. An agreement will need to be reached between the Department of Water and Sanitation, Tongaat Hulett and EWS to determine the maximum amount of water that can be abstracted for Phase 2 of the TWTW functional upgrade. Phase 2 will include upgrading the inlet channel, trunk mains and pumps in order to cater for future demand. The head of the works will be upgraded to give better assurances of water quality and how water is channelled to clarifiers and filters. “While we would have liked to have included this work in the actual repair project of TWTW, we were heavily focused on restoring water supply to the local communities as quickly as possible,” states Soni. Due to the nature of the ground conditions and surrounding buildings, heavy vibratory equipment could not be used beneath structures
Conclusion
Soni adds that while EWS has experience and expertise in the day-to-day operations of water and sanitation systems, the floods were an unusual event and the municipality was not fully equipped to deal with a disaster of that magnitude. “Going forward, there should be a national disaster management team that has already appointed contractors and consultants as well as funding in place to handle these disasters. If something like this were in place, a lot of the restoration work would have been completed more rapidly. The biggest delay in responding to disasters is a procurement process, and a national disaster management team and our own in-house construction teams can assist with quicker response times.” “This project is an example of what can be achieved if all project stakeholders work towards a common goal, in this case resulting in achieving the near impossible – the restoration of a treatment plant within 105 days,” explains Ramghulam. He adds that supplying the community of Tongaat with water after almost eight months without it was something the Naidu Consulting team will never forget. “We are glad to be able to have assisted on this feat of engineering.” The repair of the TWTW was Hope’s last project before he entered retirement. “While this was a relatively small project (totalling R48 million) when compared to other work that I have been involved in, it was a great last job for me personally, because of its huge impact on people’s lives. The team working on the project were exceptional and the high attendance record and commitment shown on-site by the workforce made the job that much easier.” The TWTW pump station with new motors, repaired pumps and suction/delivery pipe work (Credit: PCI Africa)Erosion damage on the TWTW due to flooding (Credit: Naidu Consulting/MSV JV)Construction of a new MCC building at a higher elevation to prevent future flooding damages (Credit: Naidu Consulting/MSV JV)
Corrosion – the gradual deterioration of materials caused by environmental exposure – poses a major challenge in maintaining water distribution systems. To tackle this issue, WISA hosted a seminar focused on understanding corrosion and exploring a...
The City of Cape Town recently honoured 18 organisations for their commitment to water sustainability at the 5th annual Water Star Rating Awards. To date, a total of 95 certificates have been awarded, with the programme growing steadily...
The African Union-AIP Water Investment Summit 2025 held in Cape Town proved largely successful, raising US$10 billion in investment commitments for the continent. However, water infrastructure investment needs to be equally matched by investment in...