Construction of the new inlet water pipe from the eThekwini Water and Sanitation (EWS) main line to the Jerome Drive reservoir in Kloof was completed ahead of schedule in January this year.
The Jerome Road inlet is part of the ongoing EWS Western Aqueduct project. Because it is runs past St Mary’s School, it was commissioned as a stand-alone job over the December holidays to cause as little disruption to traffic as possible. “We envisaged at the start that working along St Mary’s Road was going to be the most difficult part but, with careful forward planning, constant correspondence with the school and communication with residents, the work was carried out smoothly with few problems,” said Andrew Copley, senior area engineer for EWS. “We would like to thank St Mary’s School, parents of children at the school, residents and motorists who have been affected by the construction for their patience and understanding,” Copley said. “We know that this route is used by up to 1 000 cars every day and we did everything in our power to keep disruption to the traffic flow to a minimum. “Other challenges were laying the pipe in the 1.2m diameter jacked sleeve across the M13 and in the narrow servitude at Jerome Place,” he said. The decision to lay a completely new pipe was made to minimise leaks and conserve the city’s precious water resources and because the alternative – ongoing repairs – would be both costly and inconvenient to residents. Addressing supply
“The supply to Jerome Drive reservoir initially came from three supply feeds which could be unreliable at times, as well as expensive, because two of them were via a pumping system,” explained Leisel Bowes, project manager for EWS. “The new Western Aqueduct would have solved this problem by providing a dedicated, cost-effective supply to the reservoir but, because it is only due to be commissioned in 2016/2017, we had to consider an alternate supply.”