South Africa’s water security has mainly been reliant on surface (fresh) water and its development

Recent regulations from the department of water and sanitation (DWS) will hopefully overcome the long delays in securing water use licences and allow for a more streamlined implementation of projects, said Manda Hinsch, partner and principal water and environmental scientists at SRK Consulting.

According to Hinsch, the new regulations are a positive step that aligns the timelines for Water Use Licence Authorisations (WULAs) for those who have applied for environmental authorisations as required by the National Environmental Management Act (NEMA).

“Both processes now promise authorisations within 300 calendar days, if all documents and studies are in order,” Hinsch said. “In the past, receiving water use authorisation could take up to three to five years.”

She said these delays often led to applicants simply starting project construction without the necessary authorisation, since the positive socio-economic impact of proceeding was deemed to outweigh the negative environmental impacts.

She added that assessment processes within the department were not always well-monitored, and it was therefore difficult to track the stage at which an application within the process had reached.

“This problem should now be eliminated since clear responsibilities, with timeframes, are allocated to both the applicant and the relevant water authority,” she said.

Authorisation process

Hinsch said the process will now begin with a pre-application meeting with the water authority, followed by the submission of the application within five days. A date for a site visit then needs to be finalised by five days after that, and the visit itself must take place within the next 30 days.

She explained that the authority is then expected to respond within five days of the site visit, outlining the exact requirements for the WULA. The applicant then has 105 days to prepare and submit the necessary technical reports, as well as conduct the public participation processes.

Following submission, the authority has 10 days to acknowledge receipt of the application, and 139 days to consider the documentation and make a decision, after which it has five days to issue the decision.

“The new regulations also formalise the public participation requirements, which were neglected in the past, particularly if a WULA was required without the need for an environmental authorisation,” Hinsch said. “Another positive aspect of the regulations is that they provide structured guidance on which technical documents are required for each of the different water uses, with a complete list of contents for each use.”

These are positive steps by the DWS, she said, which now require the department to commit the necessary skills and resources to implement the regulations effectively.

“These regulated timelines are tight, and place pressure on both the department and applicants to work quickly and efficiently,” she said.

“From the applicants’ point of view, it would be wise to choose consultants who are experienced in conducting WULAs, so that deadlines are not missed,” she added. “SRK has been submitting WULAs in terms of the National Water Act, on behalf of our clients since 1998, and also works extensively with NEMA timelines. We are therefore accustomed to doing project planning to meet the various deadlines and milestones within projects.”