The project to repair the Groot Marico Bridge on the N4 is well underway with the Bakwena Platinum Corridor Concessionaire (Bakwena) implementing traffic restrictions.
The bridge, which is situated in the North West Province, is currently undergoing extensive repairs after a 150mm section collapsed. Liam Clarke, Commercial Manager of Bakwena, says the bridge collapsed as a result of flooding in the Marico River which caused years of built up silt to move compromising the bridge’s footing.Project outline
“The first part of the reconstruction process, which commenced in August 2017, involves the erection of nine temporary load-bearing support columns to keep the bridge stable and the placement of jacks at the top of each column to allow the bridge to be jacked up to its original height.” The next part of the process involves driving metal sheets down to the rock and pouring concrete and grout into the gap to reinforce the bridge’s foundation. Once this has been completed, the bridge will be jacked up to correct the road alignment.Clarke says the original bridge was 7.5 metres wide. “We widened the bridge in 2002 by 5.1m to incorporate 2.5m metre shoulder for vehicles. This part of the road is safe for road users and we are operating a stop and go along this section to allow traffic through.”