Contractors cannot suspend work over non-payment | Infrastructure news

Infrastructure

The Joint Building Contracts Committee has cautioned contractors against walking off site due to non-payment.

The Joint Building Contracts Committee has cautioned contractors against walking off site due to non-payment.

Contrary to what many contractors assume, there is no provision in most building contracts that would legally permit the contractor to suspend work if the employer fails to pay by the due date, nor are there contractual rights to remove materials and goods from site, says Uwe Putlitz, CEO of JBCC.

Putlitz says if the contractor is not paid on time, he or she would need to compel the defaulting employer to honour the contract, or seek other methods of obtaining payment. “The contractor could, for example, offer the employer payment terms and, should the employer still not pay, the contractor could then have the contract cancelled and sue the employer for damages.”

Payment categories

Putlitz says contract payments basically fall into two categories:

Interim payments

These are based on valuations prepared by the principal agent for work done at a given point. These are usually prepared monthly by no later than a specified date and repeated every month until the final payment. The valuations should represent the total amount of work carried out to date, including unfixed materials and goods procured by the contractor, less any amounts previously certified.

“While the obligation to prepare the valuation and issue the certificate rests with the principal agent, the contractor is required to assist him or her to determine the valuation by preparing and supplying a claim for payment incorporating measurements and valuations based on the bill of quantities of duly completed work, and material and goods, together with relevant documents, such as invoices.

“The valuation should incorporate the cost of work done by the subcontractors and include materials and goods supplied by them. This payment method is used in commercial and larger residential or commercial type projects,” Putlitz explains.

Progress payments

These are based on pre-determined milestones and are payments for work completed or progress achieved. For example, when the surface bed has been cast, or the roof has been installed, the contractor would then be paid the amount that was stipulated in the contract schedules. This type of payment method is used where no bills of quantities have been used and is mainly employed for smaller type projects.

Putlitz adds: “The employer is obliged to pay the amount certified, or pay the pre-determined progress payment within a reasonable time, usually seven calendar days of the date of issue of the certificate or the contractor providing the employer with an invoice for the amount certified, or for the amount of the pre-determined progress payment.”

Additional Reading?

Request Free Copy