Upgrade of the Ritchie WWTW was commissioned by Sol Plaatje Municipality as it is currently hydraulically overloaded and only running on a capacity of 0.5 Mℓ/d.
Vela VKE’s Bloemfontein office is currently responsible for the design and site supervision of the Ritchie Wastewater Treatment Works (WWTW) upgrading, which forms part of the infrastructure upgrade by Sol Plaatje Municipality – initialised by the executive director of Infrastructure and Services, Boy Dhluwayo. Situated on the town of Ritchie in the Northern Cape, the WWTW currently consists of only oxidation dams, which are being used with a capacity of 0.5 Mℓ/d and was in need of an urgent upgrade. It was therefore necessary for the hydraulic capacity of the WWTW to be increased to 2 Mℓ/d. Project overview The current inflow at Ritchie WWTW consists of mainly residential sewerage that enters the works from a pump station – no gravity inflows take place. The WWTW was designed and constructed in a cost-effective manner without compromising quality or construction standards – to comply with national government’s obligation to uplift community hygiene standards and other general expectations. The current works consist of:- two anaerobic ponds each 1 450 kℓ and 4.3 m deep
- a primary pond of 13 000 kℓ and 1.3 m deep
- a secondary pond of 19 500 kℓ and 1.3 m deep
- two tertiary pondseach 800 kℓ and 1.3 m deep
- three tertiary ponds of 2 300 kℓ, also 1.3 m deep
- construction of a truck dump facility
- construction of new inlet works complete with mechanical screen and manual standby screen
- two duty/standby horizontal flow grit channels
- inlet flow measuring station based on BS3680 flume
- upgrading of the two existing anaerobic ponds to 1 450 kℓ concrete activated sludge reactors, complete with mixing, surface aeration, mixed liquor and sludge recirculation
- construction of a new 16-diameter clarifier downstream of the two reactors for effluent clarification, settling and return of sludge from the clarifier to the anoxic reactor
- use of primary ponds as contact tank and maturation ponds after chlorine dosing
- flow from the last chlorination/maturation pond will be released to the adjacent vlei area
- a new measuring station
- last three ponds will be reconstructed and used as sludge lagoons
- electrical infrastructure complete with office buildings
- new 200 KVA, with a supply voltage of 400 V – Eskom line was built to supply the works.
Progress
Construction is currently on track with 36% of the work complete and an anticipated final completion date of 31 August 2012. Although Vela VKE still envisages several engineering challenges ahead, the biggest concern is the time frame and unruly community problems, which the contractor is encountering. The company is however confident that the project will be completed within time and budget.PROJECT TEAM | |
Client | Sol Plaatje Local Municipality |
Civil engineer | Vela VKE |
Contractor | WEC Projects |