As a leading contractor in South Africa’s drive to harness renewable energy, Concor has started work on the Cennergi Holdings and G7 Renewable Energies 140 MW Karreebosch Wind Farm. Concor will carry out the balance of plant work including all civil portions such as the roads, platforms and concrete foundations as well as the medium voltage reticulation, OHL construction, substation, buildings and grid connection.
Concor has become an important construction partner in South Africa’s wind energy landscape, and recently started work on the Cennergi Holdings and G7 Renewable Energies 140 MW Karreebosch Wind Farm.
Located between the towns of Matjiesfontein and Sutherland, Karreebosch Wind Farm is sited predominantly in the Northern Cape, and will generate energy for a private off-taker. At the heart of the project will be 25 turbines at a height of 100 m with blades over 84 m long. Interestingly, the site of this project is adjacent to the Roggeveld Wind Farm which Concor completed about five years ago. According to Stephan Venter, Contracts Director at Concor, the early work included establishing the necessary infrastructure on site, given the remote and rugged terrain. This will include access roads, site offices and a batching plant for the large volumes of concrete required for each turbine’s foundation. Concor has begun constructing about 45 km of internal access roads, allowing the transportation of components and equipment to each turbine site. Roughly 200,000 m3 of blasting are likely to be required for the roads, foundations and other work. The G5 and G7 material for layer works will be produced on site, using jaw and cone crushers feeding a screen. “The roads need to support the long heavy trucks used to transport turbine components,” says Venter.“For instance, the long turbine blades require the road design to provide sufficient turning radii as well as the right K-values to avoid trucks striking their undercarriage on uneven surfaces.”

Early project works undertaken by Concor include establishing access roads, site offices and an on-site batching plant, in preparation for the large volumes of concrete needed for the turbine foundations.
He points out that the foundation design must also align with the loading documents that are specific to each turbine supplier. The planned lifespan of these critical foundations tends to be longer than the 20 year off-take agreement, allowing for contract extensions that could see the turbines operating for up to 25 years.
The concrete foundations for each turbine measure over 20 m in diameter and are between 4 to 5 m deep, requiring about 600 m3 of concrete per foundation. The whole project will consume in the region of 25,000 m3 of concrete and 2,200 tons of reinforcing steel.“We do our own concrete mix designs and will produce the readymix ourselves using aggregate from our Tweedside tillite quarry 70 km from site,” he explains.“Material will be transported to our own batch plant on site, allowing us to cover most of the concrete value chain ourselves.”

A close-up view captures the excavation of a wind turbine base underway at Karreebosch Wind Farm, where Concor is preparing the foundation to exact specifications based on detailed geotechnical investigations.