
Arnold Sagonda, executive, project finance, Fasken

Danielle van der Vaart, partner, Fasken.
- Red Book – construction contract for building or engineering works designed by the employer, commonly used for traditional design–bid–build projects
- Pink Book – a modified version of the Red Book, adapted for projects funded by Multilateral Development Banks (MDBs)
- Yellow Book – where mechanical and electrical, building and engineering works are designed by the contractor, frequently used for process, electrical, or mechanical plant projects
- Silver Book – for engineering, procurement and construction (EPC) or turnkey projects where the contractor takes full responsibility for design, engineering, procurement and delivery, usually at a fixed price and within a fixed time
- Green Book – short form of contract for relatively simple or short-duration projects (less than 2 years, lower value)
- Gold Book – design, build and operate contract, often used in water, wastewater and energy sectors
- White Book – client/consultant model services agreement that governs the relationship between an employer (client) and a consulting engineer.
Risk reduction and allocation
Financiers look at reducing risk as well as allocating risk to the party most capable of bearing that risk. “Lenders want to move as much risk as possible away from the employer (client or project owner). Because the employer is carrying the debt, lenders want to minimise the employer’s exposure to risks that could jeopardise repayment. To achieve this, risks are shifted as far as possible downstream to the contractor or other parties who are directly responsible for the design, construction, or operation of the project. That way, if something goes wrong, the employer (and by extension, the lenders) is not left carrying the full burden. Instead, the employer has a clear contractual right to claim against the contractor or another responsible party, creating a buffer between the financing and the practical risks of delivering the project,” says van der Vaart. Contracts where there is a fixed price that is not re-measurable, a clearly stated completion time with penalties for delays and a defined allocation of risk are favoured by bankers. Contracts need to offer certainty of output, certainty of price and certainty of timeline. The most lender-friendly of FIDIC’s suite of contracts is the FIDIC Silver Book.There are allowances for sub-contracting, where FIDIC contracts will stipulate what type of work can be subcontracted, what parties can be chosen as sub-contractors and even monetary thresholds. “But the contractor will be fully liable for sub contracted work,” she adds.
Additional layers of protection are built into the contracts with bonds and parent company guarantees. “There is little point in claiming against a contractor that has run out of money, so it is important to have liquid security,” states van der Vaart.
Sagonda contrasts this with JBCC: “You’d almost have to rewrite the JBCC agreement to reach that level. Under JBCC, pricing is often linked to bills of quantities, meaning costs can fluctuate. JBCC includes provisions for variations and delays that allow contractors to claim additional time or costs. JBCC contracts also allow for a ‘cost plus profit’ approach.” When tendering under a FIDIC contract, contractors typically include a contingency allowance in their lump-sum price to cover unforeseen risks and cost fluctuations they are expected to carry under the contract. “The risk profiles under FIDIC and JBCC are different. Under FIDIC, risk is largely shifted to a contractor. But with JBCC, contractors can often claim additional costs and time extensions for unforeseen conditions, which shifts more risk back to the employer. That difference in risk profile is one of the reasons financiers see FIDIC as a safer choice,” Sagonda explains. FIDIC contracts typically cap liability at 100% of the contract price, with exclusions for gross negligence or wilful misconduct, amongst others. Lenders will look at ‘worst case scenarios’ and model what level of risk the project can tolerate and thus what the likelihood is of reaching the liability cap. Insurance regimes vary by project and insurance cover will be taken out to provide another layer of risk mitigation. JBCC, however, has lighter insurance requirements given its focus on smaller works, and notably lacks standardised liability caps and consequential losses provisions.
Dispute resolution and enforcement

Tania Siciliano, partner, Fasken.