With a view to strengthening the long-term water security for KwaZulu-Natal’s South Coast, construction of the Ngwadini Dam, a key component of uMngeni-uThukela Water’s Lower uMkhomazi Bulk Water Supply Scheme (LUBWSS), has made significant progress.
Appointed by uMngeni-uThukela Water, GIBB is responsible for the detailed design, construction supervision and contract administration of the dam, helping to ensure that this strategically important infrastructure is delivered to the required engineering, quality and safety standards. Jacques du Plessis, GIBB Technical Executive, says with construction commencing in January 2024, the dam has made excellent progress, with the contractor reporting only approximately one month of schedule slippage to date, largely attributable to flooding experienced in February 2025.“This performance is particularly commendable given the challenging site conditions and the complexity of constructing major water infrastructure in a remote river valley.”
A strategic investment in regional water security
The Lower uMkhomazi Bulk Water Supply Scheme is designed to augment the supply of potable water to KwaZulu-Natal’s South Coast. The broader scheme involves abstracting raw water from the uMkhomazi River at Goodenough Weir and conveying it to a new Lower uMkhomazi Water Treatment Works. Following treatment, potable water will be supplied to the South Coast System’s Quarry Reservoir. Ngwadini Dam plays a critical role in this integrated system by providing off-channel storage that can be used to supplement low flows in the uMkhomazi River when required. Water can be released from the dam into the river to support downstream abstraction and treatment, helping to improve the reliability of water supply during periods of reduced river flow. Du Plessis says by locating the dam outside the main river channel, the scheme avoids the dam silting up during large flows in the uMkhomazi River that could compromise the long-term usability of the reservoir. “A separate abstraction and pumping facility at Ngwadini Weir will enable the dam to be replenished during the rainy season.”A major engineering project taking shape
Ngwadini Dam is a substantial rockfill embankment structure incorporating a concrete face slab. Once completed, the dam will be about 52 metres high, with a crest length of 300 metres. The project’s key engineering specifications reflect the scale of the undertaking:- 10.1 million cubic metres of live storage capacity.
- 10.6 million cubic metres of total storage capacity.
- 511,600 cubic metres of rockfill in the dam embankment.
- Approximately 1.4 hectares of concrete face slab.
- Approximately 26,000 cubic metres of concrete used in the dam works.
Construction milestones and progress
Du Plessis notes that the dam construction has advanced through several significant stages. “Rockfill placement has been completed to the base of the parapet wall, while work continues on the concrete face slab starter panels and the intake tower.“The contractor is also progressing with the spillway concrete works. Other works include placing the concrete face slab panels, completing the parapet wall and associated backfilling and finalising the access roads and site rehabilitation,” he adds.Installation of the bridge beams providing access to the top of the intake tower is planned for early 2027, followed by construction of the control building. The concrete face slab works are expected to continue into mid-2027. Construction of the dam is currently scheduled for completion by the end of August 2027.
GIBB’s multidisciplinary role
GIBB’s contribution extends beyond the engineering design of the dam. Their scope included preparation of the tender design, technical specifications and bill of quantities, and preparation of the tender and contract documentation. After the contractor was appointed by uMngeni-uThukela Water, GIBB undertook the detailed design and commenced construction supervision. The company also provides contract administration services on behalf of the client and as construction progresses towards completion, GIBB will also prepare the construction completion report, documenting quality records and programme performance, amongst others. The scope includes the development of an operating and maintenance manual and an emergency preparedness plan for the dam.Dave Wing, GIBB Project Manager says in addition to Ngwadini Dam, GIBB is involved in the wider LUBWSS programme, providing engineering and project delivery support across the scheme’s various infrastructure packages. “These include the Goodenough abstraction works, the Ngwadini abstraction works and the bulk water supply pipeline.
“GIBB’s role across these packages encompasses design, construction supervision and contract administration, supporting coordinated delivery of the broader water supply system,” he adds.