Construction of the Polihali Dam, the massive concrete-faced rockfill dam (CFRD) being constructed in the Lesotho eastern highlands under Phase II of the Lesotho Highlands Water Project (LHWP) is now 50% complete and is on track for the start of impoundment in the 2027/2028 rainy season.
With the construction of multiple elements of the Polihali Dam infrastructure underway simultaneously, the site is a hive of activity and construction achievements.Recent construction milestones on the main dam include reaching elevation 2 020 on the rockfill and upstream concrete curb in mid-May slightly ahead of the construction programme timelines. By the end of June the upstream concrete curb and rockfill had reached the 2 024 metre elevation. With a total of 9.6million cubic metres of rock placed at an average of 26 000 cubic metres per work day, the rockfill on the 166-metre high concrete faced rockfill dam is now 67% complete. The next step is to raise the rockfill on the downstream side of the dam to equal the upstream rockfill and concrete curb; thus achieving the third milestone.

Polihali Dam Downstream tunnel portal

Polihali Dam Outlet Tunnel
The spillway, another extremely large concrete structure, also continues both with final excavation and concrete construction. Excavation of the plunge pool is also underway.
While the physical construction progress is clearly visible, there are other achievements on the Polihali Dam project which are a source of pride to the LHDA and the project team. These include its zero fatalities and high lost time injury-free numbers, and that it has created employment for many people. By the end of April that figure stood at 2 709 people. Of these, 2 062 are semi-skilled employees, 99% of whom are Basotho nationals, contributing to enhancing skills and hands on learning in the country. The Polihali Dam is approximately one kilometre downstream of the confluence of the Khubelu and Senqu (Orange) rivers. It will create a reservoir capable of storing 2 325 million cubic metres of water and will enable water delivery to South Africa to be increased incrementally from the current 780 million cubic metres per year to 1 270 million cubic metres annually. As construction progresses toward its expected completion in 2029, the Polihali Dam is testament to what can be achieved through innovative engineering, international cooperation, and a vision for sustainable development. It is not just a dam; it is a catalyst for regional transformation enhancing water and energy security and regional connectivity. The Lesotho Highlands Water Project is a model for large-scale infrastructure projects enhancing the LHWP’s position as Africa’s benchmark in cutting edge engineering at high altitude. 2026 marks the 40th anniversary of the signing of the LHWP Treaty, a proud moment in the history of the project and the Lesotho Highlands Development Authority.
