Klapmuts Railway Bridge Set For Final Sideways Launch This Weekend | Infrastructure news

Smart Civils is preparing to slide a railway bridge deck into its final position this weekend as part of a R52 million underpass project in Klapmuts. The first stage of the launch is complete. For the second stage, both electrified railway lines will be taken out of service, with 12 hours allocated to move the deck before track reinstatement begins.

The underpass will span a new access road and carry railway lines operated by Transnet and the Passenger Rail Agency of South Africa (PRASA). The route carries freight between Cape Town and Gauteng as well as local commuter services. The contract, which began in November 2025, also includes a traffic circle on Old Paarl Road and associated engineering services for The Bridge: Stellenbosch development. UDS Africa is the consulting engineer.

Klapmuts railway bridge before construction photo

Klapmuts railway bridge before construction

The original design called for precast beams supported on cast-in-place longitudinal beams. Smart Civils proposed a cast-in-place, post-tensioned beam-and-slab deck supported on piled capping beams. The revised design allowed the deck to be built alongside the railway and slid into position on steel I-beams, reducing the time both tracks needed to be closed.

“We built the deck alongside the railway so we could carry out much of the concrete and post-tensioning work while trains were still running,” says Danie van Wyk, site manager at Smart Civils.

“The first move took the deck approximately halfway across, allowing Transnet to reinstate the track over the deck and resume services between the two stages.”

Klapmuts railway bridge Excavation for Culvert

Preparing the path for the launch meant constructing permanent crossbeams through the railway embankment. Smart Civils installed temporary culverts to provide access for that work. The crossbeams support the deck during the launch and in its permanent position, and their alignment affects the force needed to slide it into place.

During the week, at least one of the two tracks must remain available. Transnet requires 21 days’ notice for full closures, which are available from 21:00 on Fridays to 18:00 on Sundays. The final move requires both tracks to be closed because the deck cannot be jacked into position while trains are running.

Klapmuts railway bridge being built in sand

“We have 12 hours allocated to move the deck into its final position,” says Van Wyk. “From there, the railway team still needs time to reinstate the tracks before passenger services can resume. That handover is what we work back from when we plan the move.”

Once the deck is in position, Smart Civils will lift it onto its permanent bearings, install the barriers and complete the remaining bridge works. The project will be completed by February 2027.

Klapmuts railway bridge casting

www.smartcivils.co.za